HERE WE GROW AGAIN
January 15, 2021
Drywall completed. Grid completed. Lights completed. Vinyl Flooring completed.
January 4, 2021
December 21, 2020
December 10, 2020
November 30, 2020
Demo work and framing.
November 19, 2020
Fire final. Building final C.O.
November 10, 2020
Final Paint. Fire alarm and emergency lights inspection (passed).
October 29, 2020
Floating out the drywall. Restroom lights. Final ceiling tile.
Final Electric inspection. Final HVAC inspection. Final paint.
October 19, 2020
Installation of counter tops. Doors and trim. Final plumbing inspection.
October 8, 2020
Started floor tile and carpet start baseboards and cabinets.
Tile ceilings and install the restroom fixtures.
September 28, 2020
Continue with painting and the ceiling grid
September 18, 2020
Start painting and start the ceiling grid
September 8, 2020
Finishing sheetrock and start priming.
August 27, 2020
Start sheet rock
August 17, 2020
Framing ceilings and completed electrical rough in.
August 6, 2020
Set iron for divider curtain. Start framing and rough plumbing for restrooms and break room.
July 27, 2020
Poured back plumbing slab for restrooms. Formed footers and poured concrete.
Installed 2 inch pipe across the corridor for cable fiber.
July 17, 2020
Started electrical rough in. Cut slab for columns.
July 7, 2020
Started work on demolition and disconnecting power and plumbing.
June 17, 2020
New space, ready for renovation